On October 4, 2005, the Minnesota Court of
Appeals decided a case which should make every
subcontractor think twice about the language
used in its construction bids. The Court affirmed
that Beaver Masonry (a masonry business owned
by Craig Shuck from Spicer, Minnesota) must
pay $78,522 to Riley Brothers Construction
(a construction company located in Morris
Minnesota). What did Craig Shuck and Beaver
Masonry do to justify this judgment? They
provided a bid for road construction to Riley
Brothers Construction which turned out to be
too low by $78,522.
The Facts:
In the spring of 2002, the City of Wahpeton,
North Dakota, sought bids for road construction.
Craig Shuck learned that Riley Brothers
Construction was preparing a bid as general
contractor and contacted the company to obtain
bid specifications. Based on the specifications,
Beaver Masonry submitted the lowest bid. In
turn, Riley Brothers submitted a bid to the City
of Wahpeton (incorporating Beaver Masonry's
bid) and won the contract.
On May 22, 2002, Mr. Shuck attended a
construction meeting for the Wahpeton Job. At
the meeting, Mr. Shuck reviewed the blue prints
and determined that his company's bid failed to
take into consideration several of the job's
specifications. The blueprints called for three
foot slabs, reinforced concrete and required
compliance with the “Davis-Bacon Act” none of
which were contemplated by the bid. The
evidence shows that rather than disclose the
error during that meeting, Mr. Shuck waited until
June 11th to inform Riley Brothers Construction
that he would require an additional $80,000 plus
additional costs to complete the project. Rather
than negotiate with Mr. Shuck, Riley Brothers
Construction hired the next lowest bidder, completed
the project and then sued Mr. Shuck and Beaver
Masonry based on theories of breach of contract
and promissory estoppel. Beaver Masonry's defense
was that its bid did not constitute a binding
contract, as everyone in the construction industry
knows that there is no “contract” until a formal
construction contract is signed.
The Court's
Decision:
Unfortunately
for Beaver
Masonry, the
court agreed
with Riley
Brothers Construction and held that there was a
binding contract which had been breached by
Beaver Masonry. The court found that the bid
was an offer which was accepted by Riley
Brothers on May 21st when it asked Mr. Shuck to
attend the construction meeting. The court also
found that even if there wasn't a contract, Riley
Brothers had relied to its determent on Beaver
Masonry's bid resulting in a claim for promissory
estoppel.
Practice Points:
- Both Contractors and Subcontractors should
be clear on specifications for bids. Neither
party wins when bids don't reflect the true
cost of construction.
- If you make a mistake in the bidding process,
bring it to the other party's attention as
soon as possible. Mr. Shuck's failure to
communicate the problems with the bid once
he knew of them may have factored into the
court's ruling.
- If a bid is not intended to be an offer, include
a disclaimer such as the following: This bid is
based on the specifications provided by the
General Contractor. Changes in the
specifications or additional requirements not
disclosed in the specifications may impact the
cost of construction and this bid. This bid is
not binding on Subcontractor except to the
extent the bid is incorporated into and part of
a final construction contract signed by both
Subcontractor and General Contractor.
Founded in Saint Paul in 1943, Felhaber, Larson,
Fenlon and Vogt, P.A. has offices in Minneapolis and Saint
Paul. With over 55 attorneys, the firm serves clients in
the areas of corporate and commercial law, employee benefits,
employment law, estate planning, health care, intellectual
property, labor law representing management, litigation, real
estate, transportation law, and workers' compensation.