Last year, a case decided by the Wisconsin Court of
Appeals placed contractors in that state on notice. In
some jurisdictions, if you sign and deliver a lien
waiver without getting paid, the owners have a right
to rely on it. The case was Tri-State Mechanical, Inc.
v. Northland College, 681 N.W.2d 302 (Wis.App.
2004), and the facts were as follows:
The Facts:
Northland College (“Northland”), the owner,
contracted with Frank Tomlinson Co. (“Tomlinson”),
the general contractor, to build a new science
building. Tomlinson subcontracted with Wynn O.
Jones & Associates, Inc. (“Jones”) to provide labor
for the installation of the science lab. The subcontract
contained a lien waiver provision that required
Jones to provide a properly executed release and
waiver of liens “as an explicit condition precedent to
the accrual of Jones' right to final payment.”
Jones performed all the necessary work and submitted
the final mechanic's lien waiver. While Northland
paid Tomlinson the full contract price of nearly $5
million pursuant to their contract, Tomlinson never
paid Jones and Tomlinson went out of business.
Jones then filed a mechanic's lien against Northland,
and another subcontractor, Tri-State Mechanical, Inc.,
also filed a lien and started a lawsuit.
In court, Northland argued that Jones' mechanic's lien
waiver extinguished all mechanics's lien rights. The
court agreed, and ruled that Jones could not maintain
a lien claim because of the mechanic's lien waiver.
Jones appealed, arguing that a Wisconsin law
invalidated the mechanic's lien waiver provision in
its subcontract. The appellate court agreed that the
Wisconsin law invalidated provisions in construction
contracts that required a subcontractor to waive its
right to a construction lien before payment. The
appellate court, however, disagreed with Jones'
argument that the Wisconsin law consequently made
the Jones' lien waiver void. The appellate court
found that the Wisconsin law provided a
subcontractor facing a void mechanic's lien waiver
provision with a choice: “it can either tender a lien
waiver prior to being paid or refuse to do so until it
is paid. By giving the subcontractor a choice, the
legislature has essentially made a policy decision that
endorses whatever
course of action the
subcontractor takes.”
The appellate court
concluded that because
Jones furnished the mechanic's
lien waiver before receiving payment, it also accepted
the risk of nonpayment. Jones was left without the
ability to file a lien against the property and without
the ability to collect money because the general
contractor was out of business.
How Problems Arise:
Nearly all construction contracts require the contractor
to provide a partial mechanic's lien waiver in order to
receive payment. It is a routine part of the construction
process. The fact that it is routine is also why it can
be so dangerous. A contractor must use care when
agreeing to sign a mechanic's lien wavier prior to
receiving payment because a contractor who fails to
review (and if necessary revise), the waiver risks
losing the right to recover on future claims.
Tips for Avoiding Trouble:
- In some jurisdictions, you should insist on
payment. In the case presented above, Jones would
have been better served by refusing to sign the
mechanic's lien waiver until payment was made,
or insisting on use of an escrow agent to facilitate
payment prior to release of the lien waiver. In
Minnesota, the law protects contractors who are
forced to sign a lien waiver prior to receiving
payment. (Minn. Stat. § 337.10) In Minnesota, a
contractor can sign a partial mechanic's lien waiver
without jeopardizing its right to seek payment. If,
however, an owner or purchaser takes some action
in reliance on the partial mechanic's lien waiver,
the mechanic's lien waiver will be enforced.
- Avoid signing lien waivers that cover “all claims”
if there are additional claims for work performed
or if there is future work to be performed. If
there has been or will be additional work
performed, add details regarding this to the
waiver to put the owner on notice.
- Avoid release language. A “release” is much
broader than a “lien waiver,” and will be
interpreted as such by the courts.
- Add language such as “released upon receipt of
payment” to clarify that the lien waiver is conditioned on your receiving payment.
- If you have questions about the language in
a mechanic's lien waiver or the timing of
providing a mechanic's lien waiver, you
should seek competent legal advice.
(This article contains a general discussion of the
law. This article does not constitute and should not
be treated as legal advice as to any particular
situation.) Readers are encouraged to submit any
comments to the attorney listed below.
Founded in Saint Paul in 1943, Felhaber, Larson,
Fenlon and Vogt, P.A. has offices in Minneapolis and Saint
Paul. With over 55 attorneys, the firm serves clients in
the areas of corporate and commercial law, employee benefits,
employment law, estate planning, health care, intellectual
property, labor law representing management, litigation, real
estate, transportation law, and workers' compensation.